AN ALTERNATIVE METHOD OF INCREASING THE TRANSMISSION PERFORMANCE OF A CONVENTIONAL 110 kV CABLE LINE
(Journal of Energy Technology, 2019-11)
The purpose of this paper is to show that a significant increase in the ampacity of a 110 kV underground cable line is achievable, if a hydronic asphalt pavement system is applied along the entire
line, and if the cable ...
Eliminating the effect of hot spots on underground power cables using cool pavements
(Electrical Engineering, 2019-10-24)
It is well known that hot spots limit the ampacities of underground power cables. There are many commonly applied methods
to control the thermal environment in hot spots of underground power cables. However, applications ...